|
©2006
THEJUBILEERIVER.CO.UK
Since the conception of this
ambitious engineering project, the specification of the
Maidenhead Windsor and Eton Flood Alleviation Scheme (MWEFAS)
was revised continuously so it could meet its flood
alleviation and environmental objectives within the existing
financial constraints. The level of its success will depend
entirely upon how well it has met those objectives.
When the Maidenhead Windsor
and Eton Flood Alleviation Scheme (MWEFAS) faced its first
major test in the January 2003 floods, the Flood Risk Action
Group’s (FRAG) Mechanism of Flooding (MOF) report revealed
that the MWEFAS eventually passed only 144 m3/s
of flow in the Jubilee River, 5m3/s of flow in
the Maidenhead Ditch and 244m3/s of flow in the
River Thames. This means there was a total of only 393m3/s
of water flowing through the scheme in comparison to the
objective of 515m3/s (only 76% of its intended
maximum capacity), therefore it has
been unsuccessful in reaching its objective. The
reason for this was finally revealed in the Atkins hydraulic
and technical reviews through a
catalogue of errors in the design of the major
structures that control the flow throughout the Jubilee
River. |
|
The question must be asked,
are the taxpayers now expected to pay for the repairs or
could the people who designed and constructed the Jubilee
River pay for it instead? This would be a difficult question
to answer because of the legal and political implications.
Firstly, there were a great number of consultants and
sub-consultants that worked on the design and construction
of the scheme
(NRA
1992h) and the Environment Agency would have trouble
identifying those directly responsible. If the Environment
Agency were to try and recover costs from the designers and
contractors, it is likely that they would opt for a
settlement instead of risking damage to their reputations
and brand image. Besides this, the Environment Agency was
fully informed of all of the decisions made with regards to
design. Also they didn’t follow the
recommended operating procedures for the Jubilee
River so it may be difficult to take the case to court. |
|
Accessing the success of the
defences at Cookham is difficult because the flood banks
around Cookham were not scheduled for completion until after
the 2003 floods. During the floods, emergency works were
used to lessen the effect of the flooding. However, to the
local residents, this is understandably seen as another
failure of the scheme. The flood banks were completed in
spring 2003
(FRAGS,
2004) within the original budget of the scheme. This has
not, however, solved the problem. Owing to the higher than
expected water levels at Strand Lane in Cookham, remedial
works are currently underway to raise the standard of
protection in the area to pre-MWEFAS levels. Also, the
existing dip in Strand Lane is to be filled in to facilitate
the raising of the road level and maintain access. The
Environment Agency has forecast an additional expenditure
for this as 3.5million pounds over three years
(Environment Agency, 2004c). This represents a
significant failing in the design objective with substantial
extra costs to correct it. |
|
The analysis of the
available information illustrates that the design of the
scheme exacerbated the flooding
downstream of the Jubilee River for a number of
reasons. The fundamental reason is due to the errors in the
design and construction of the Jubilee River that has
reduced its capacity to just 67% of its design objective. As
a result of this, the Environment Agency operated the MWEFAS
differently from the operating procedures throughout the
January 2003 flooding to alleviate the flooding. This, in
turn, led to the Environment Agency failing to react to the
fact that the speed of the River Thames flood peak from
Maidenhead to Windsor took an additional 12 hours, when in
the past the use of the flood plain slowed the speed of the
flood peak from 2 to 2½ days. This meant that the
Environment Agency then failed to
divert the rising flood peak into the Jubilee River
at an early stage of the flood event in line with the
original operating intent. An additional failure was that
the Environment Agency failed to understand the importance
of closing down the Jubilee River as the peak commenced to
drop at Maidenhead, with the result that the Jubilee River
was continuously flowing at maximum channel volume when the
natural peak of the flow through the MWEFAS passed through
the confluence above Datchet. |
|
Although it did not play a
part in the 1992 Public Inquiry the issue of dredging of the
Thames has been emphasised in light of the problems
downstream of the MWEFAS. There was a continuous dredging
programme from 1947 to 1995
(Flood
Risk Action Group, 2004). This was terminated in 1995
and failure to continue a dredging
programme has meant the loss of water volume capacity
particularly in Wraysbury, Ham Island and Old Windsor. There
is the possibility that with the addition of the Jubilee
River, the overall flow in the Thames has decreased in areas
and there is the potential that siltation may have increased
thus reducing the capacity of the Thames further. This
review cannot make any firm judgments on this as there is no
data available. |
|
While the MWEFAS is
operating below its intended design objectives, it creates a
development planning problem for the Borough Councils
located within the schemes boundaries. This is because they
have based their planning decisions upon information in the
2001 flood maps but because of the reduced level of flood
protection, the Environment Agency will now object to
applications based on these maps in the future. This leaves
the local Borough Councils to operate using pre-MWEFAS flood
maps, resulting in a very confusing situation for the
councils and the public. |
|
Also, thousands of
householders downstream from the Jubilee River now face the
prospect of being flooded again by the scheme. However this
is not their only worry. There are insurance problems such
as many residents dare not claim for damages caused by the
flood because of the fear of becoming uninsurable. Also the
loss of property values is conservatively estimated in
excess of £30 million in Wraysbury and Old Windsor
(Thamesweb,
2003). |
|
The success of the
environmental enhancement of the scheme is almost equal in
value to the scheme’s flood alleviation success. The
analysis of available ecological monitoring shows that in
comparison to the management objectives, the Jubilee River
is developing into a precious wildlife and recreational
resource for the area. Most of the mosaics planted for
grassland and woodland areas have been successful and are
developing on course with the aid of minor management
techniques. The marginal and in-stream flora has faired less
well with a noticeable domination of filamentous algae due
to high nutrient levels. This is the only result of concern
as the correct management of the situation will be vital if
the scheme is to meet its water quality objectives in the
long term. In terms of the fauna in the area there are
already a number of notable examples of success. These can
be seen in the discovery of many ground beetles, successful
breeding of the little ringed plover and the mandarin duck.
Less successful points have been the instability of the
islands and gravel banks, also the Bat boxes and hotel.
Hopefully with the continued monitoring and careful
management, the water course will mature and the habitats
develop in time. This will hopefully create a greater
diversity and bring the colonisation of many of the
desirable species in the management objectives. |
|
The Future
The Environment Agency has
already completed a lot of the remedial works necessary to
restore the scheme to its capacity set out in the design
objectives but it will not be completely finished until
2006/7. This has caused understandable concern for residents
who fear flooding in the intervening periods and put the
topic of future flood defence options for the Lower Thames
region, to the top of the agenda. Local residents could not
understand why the scheme was not extended all the way to
Teddington Lock (where the Thames becomes tidal) so the
problem isn’t passed from one town to the next. This was
actually considered as part of the original feasibility
study for the MWEFAS but ruled out on cost benefit analysis.
In terms of flood
alleviation, this review has shown the MWEFAS as very
unsuccessful in meeting its objectives. The cost of the
scheme over time has risen from estimated costs of £48.6m in
1991
(NRA, 1992a) to £73.4m and then £110m. It now has the
addition of approximately £5m
(Environment Agency, 2004c) for repair but when
completed, the Environment Agency say the floodplain will be
defended and the original financial benefits will stand.
Although proof of this will have to be found in the future. |
|
Overall,
the environmental enhancement of the scheme is a great
success and is on its way to becoming a unique wildlife
corridor that will attract species to the area that have
previously been lost through development on the River
Thames. The true value of a non-market good, such as the
Jubilee River, is very hard to assess but such an asset to
the community should never be undervalued.
In the
long term the scheme will be successful because the
environmental value of the scheme will offset the expense
caused by the temporary flood alleviation failures. However,
because of the cost of the scheme to the taxpayer and the
vast number of people that rely on it to protect them, the
success of the scheme will be debated for years to come. |
|