From: Public Accounts Committee [pubaccom@parliament.uk]
Sent: 28 March 2007 17:53
To: ecwlarcombe@gmail.com
Subject: Jubilee River scheme
Dear Mr Larcombe,
Thank you for your email of 31 January to Edward Leigh, Chairman of the
Committee of Public Accounts, about the cost and operation of the Jubilee River.
As my colleague Phil Jones told you, we passed the matter to the National Audit
Office (NAO), who had recently looked at the Jubilee River Scheme and their
findings are set out in the attachment to this email.
The NAO focused their enquiries on the costs incurred on the construction of the
scheme and the subsequent works to rectify design faults and damage caused by
the operation of the scheme in January 2003. They found the scheme had indeed
cost more than £108 million (some £24 million more than budgeted, once figures
are adjusted for inflation) and only operates at approximately 87% of its
original design capacity, following completion of remedial work to repair damage
sustained during January 2003. The cost over-runs were largely due to a lack of
milestone checks in the Environment Agency’s (the Agency) project management
procedures, which have since been substantially revised.
The NAO also reviewed the appointment of the chair of the Flood Risk Action
Groups, and found no evidence that he was not sufficiently independent, although
the Agency acknowledged the shortage of suitable alternative candidates.
Finally, the NAO looked at the steps being taken by the Agency to address the
risk of flooding downstream of the river. The Agency’s Lower Thames Strategy,
commissioned in response to the 2003 floods is currently considering a number of
options to reduce the risk of flooding between Datchet and Teddington Lock. This
will, I hope, go some way towards addressing your concerns.
Thank you for bringing this matter to the attention of the Public Accounts
Committee.
Yours sincerely,
Mark Etherton
<<NAO Examination of the Jubilee River Scheme.doc>>
Mark Etherton
Clerk
Committee of Public Accounts
House of Commons
7 Millbank
London SW1P 3JA
www.parliament.uk/parliamentary_committees/committee_of_public_accounts.cfm