Transcript of 'You and Yours' Radio 4 programme - Thursday, 12th May 2005
RADIO TRANSCRIPT REGARDING JUBILEE RIVER (from Thamesweb)
Please find below the transcript of a recent Radio 4 Programme which Clive
Onions, who was Chairman of the Flood Risk Action Groups (FRAGS), circulated to
all FRAG members when he issued the minutes of the last FRAG meeting held in
April 2005.
Transcript of 'You and Yours' Radio 4 programme - Thursday, 12th May 2005
Roger Waite: A new flood relief channel for the River Thames may have to be
built to protect almost 30,000 people whose homes are at risk of flooding. They
all live downstream of a flood defence project built three years ago - the
Jubilee River, which cost 110M. It's emerged though that the design of the
project was 'modified' in what is known as a value engineering project, in other
words to save money on the original scheme, and people living in homes that were
flooded in 2003 are convinced that this is one reason why another new set of
flood defences is now being suggested. Well Melanie Abbot can tell us more. Tell
us first Mel what the Jubilee River is?
Melanie Abbot: Well it's a man-made channel and is the Environment Agency's
biggest ever inland flood defence project. It cost 110M. Although man-made, it
was built to look as much like a natural river as possible and was considered
very innovative at the time. It's seven miles long and is designed so that water
goes into the channel upstream of Maidenhead in Berkshire and returns to the
Thames, downstream of Eton. The first time it was used it protected 1,000 homes
upstream but 500 homes downstream suffered the worst flooding since 1947.
Roger Waite: So these are the people presumably who think this value engineering
exercise, as the euphemism goes, is linked to their flooding?
Melanie: Well, their confidence certainly hasn't been raised by these
revelations about this cost cutting exercise, value engineering exercise, and of
course the phrase hasn't gone down too well with them either. A report written
by the Contractors, Balfour Beattie, describes how they and the Environment
Agency at the time had a 'get to know you' dinner followed by several 'getting
to know you really well' drinks, and during this time they reviewed every aspect
of the design and considered all changes, ranging from (the report says) the
'conventional' to the 'bizarre'. Ewan Larcombe is a Parish Councillor in
Datchet, one of the areas which was flooded.
Ewan Larcombe: In 1999 the Client, that's the Environment Agency, the Designers,
and the Construction Contractors, they all got together and used
this value engineering technique to change the design of the Jubilee River. Now
I am exceedingly unhappy about that because in 1992, at the Public Inquiry, all
these designs were on paper and they were submitted in evidence at the Public
Inquiry. The Inspector's Report was written, here we have the Environment Agency
and their Contractors, working together to change the design. Now that was never
put before the public and they have implemented design changes that I believe
changed the performance of the construction.
Melanie: Now the contractors, they said that their value engineering exercise
was designed not to change the quality of the design, not to change the content
of the design, not to change the environmental impact of the design, but to do
the same thing, but cheaper. Is there anything really wrong with that?
Ewan Larcombe: You have only to look at the very first time they put water
through the Jubilee River in January 2003. Significant segments of the
construction were damaged. Surely there is something wrong here? This is £110M
world class award winning scheme that fell apart the first time that it was
used.
Melanie: And Ewan Larcombe (speaking there) does think that there should still
be a Public Inquiry into that flooding.
Roger Waite: And in the meantime we have these new proposals being put forward.
Melanie: That's right, there are five different approaches outlined to tackle
the problem: (i) it does involve building new channels to divert the flow of the
River Thames away from those areas liable to flooding. This could cost up to
200M, it would take 10-15 years to complete and would need to be approved
directly by the Treasury. Another suggestion is what is known as 'river bed
re-profiling'. Attempting to make the river deeper and perhaps wider. There are
less ambitious options such as temporary barriers and an enhanced flood warning
system. Now these suggestions - the
Environment Agency says in its announcement - are a direct response to extensive
flooding in January 2003 which affected those 500 homes.
Roger Waite: And what has been the reaction to those ideas?
Melanie: Well, 'luke warm' I think would be the word. Gillie Bolton, who lives
on Ham Island in Old Windsor, she spent days only being able to get to her house
by canoe back in 2003. She now sits on the pressure group 'ThamesAwash' which
was set up to tackle the flood risks.
Gillie Bolton: We are delighted that they are looking at these proposals, but so
much more work has got to be done, because they are talking about new channels,
and in my opinion, until they have the Jubilee River working
properly and effectively, how can they consider building new channels. They are
talking about river bed re-profiling and again, I believe that this comes in
with the dredging, but perhaps to a wider issue.
Roger Waite: Gillie Bolton, but is there real clear evidence now to link the
Jubilee River with the flooding of people's homes?
Gillie: There have been independent studies carried out to show that the Jubilee
River didn't contribute to those floods, but there has also been a study by
independent engineers called Atkins, which pointed to a long list
of design problems with the channel, as we reported on 'You and Yours' last
year. These include things like a convex weir, which arches the opposite way
from what you would normally expect, no mechanism to slow down the flow of
water, and the report also said that the channel was operating at only 80% of
the intended capacity, and this is interesting, because it was something
predicted at the original Planning Inquiry back in 1992, by Peter Ackers, a
Civil Engineer, who has now retired, but who assessed the plans at the time, and
he wrote then "that it would be very embarrassing for all concerned if the
intended capacity wasn't achieved, saying that it's not an issue that could be
clouded over and any deficiency would bring widespread and justified criticism",
and I asked him what prompted this conclusion.
Peter Ackers: It was the largest drainage scheme that had ever been built and it
had many novel features, it was in a very sensitive area, and it was fairly
obvious that if it failed to achieve its objectives, then there would be plenty
of people there to complain.
Melanie: And what in particular about the scheme made it different from other
schemes which concerns you, and perhaps led you to believe that it may be quite
difficult to predict the capacity of the channel?
Peter Ackers: The fact that it was following the latest good practice of very
natural looking channels, fitting much better into the landscape, but from the
high prerogative point of view, that made it very difficult to predict just what
its flow capacity would be.
Melanie: Peter Ackers. And he also told me that at the time, no research had
been done into the capacity of natural flood relief channels designed in this
way.
Roger Waite: And what does the Environment Agency have to say about all of this?
Melanie: Well I spoke to Ian Tomes, the Area Flood Defence Manager, and asked
him first what he thought about Peter Ackers' perhaps rather far sighted
comments.
Ian Tomes: What I would say is that at the time, the best available information
was used to design the scheme. You have to remember that the hydraulic or the
computer model that was used, was right back in the 1990's, this was scrutinised
by the Public Inquiry by hydraulic consultants, and was found to be perfectly
OK. What's happened is that we have the flooding of 2003 which has given us a
lot of new information about the Thames' flows and levels, and if we designed
the scheme now with that new information, it may be different.
Melanie: To people living downstream then from the Jubilee River that might
sound almost as if they were being used somewhat as guinea pigs for this scheme?
Ian Tomes: Not at all, as I have said already the best available information
that was available was used at the tome. It was scrutinised at the Public
Inquiry by independent experts and they didn't have a problem
with it.
Melanie: Why is there now then a need for this new strategy to those people
living downstream of the Jubilee River, they have been saying that it does
look like an admission of failure of the scheme?
Ian Tomes: No not at all, one of the highest areas of flood risk in the country
with nearly 12,000 properties at risk in a 1:100 year flood event, is the area
downstream of the Jubilee River, between Datchet and Teddington, and that risk
has always existed.
Melanie: What about this 'value engineering' exercise with something as
controversial as the Jubilee River - how wise is it to shave off the costs by
changing the design or altering the materials used.
Ian Tomes: I think the first thing I would say about that is that value
engineering is not about driving down the cost, it's an error to think that it
is. It's actually a standard industry approach really which has been used for
many years on large construction projects, it's about optimising the mix of
cost, performance and fitness for purpose. The other thing I would say is of
course that at a Public Inquiry, the detailed design is never done before a
Public Inquiry.
Melanie: But if it's not about driving down costs then why would the contractor
(Balfour Beattie) write this report really trumpeting how well they had managed
to limit the cost of the project.
Ian Tomes: Well I mean, yes, the cost is one element but its optimising that mix
of both cost, performance and fitness for purpose, so reducing the cost may be
one outcome, but also getting better performance and better fitness for purpose
may be another outcome as well
Melanie: Ian Tomes from the Environment Agency speaking to me then.
Roger Waite: Thank you for speaking to us Melanie Abbot.
End of discussion.